| News |
|
| Eric J. Lerner |
| What's wrong with the electric grid? |
|
The warnings were certainly there. In
1998, former utility executive John
Casazza predicted that “blackout risks will
be increased” if plans for deregulating electric
power went ahead. And the warnings
continued to be heard from other energy
experts and planners.

So it could not have been a great surprise
to the electric-power industry when, on
August 14, a blackout that covered much of
the Northeast United States dramatically
confirmed these warnings. Experts widely
agree that such failures of the power-transmission
system are a nearly unavoidable
product of a collision between the physics of
the system and the economic rules that now
regulate it. To avoid future incidents, the
nation must either physically transform the
system to accommodate the new rules, or
change the rules to better mesh with the
power grid’s physical behavior.
Understanding the grid’s problems starts
with its physical behavior. The vast system
of electricity generation, transmission, and
distribution that covers the United States
and Canada is essentially a single machine—
by many measures, the world’s biggest
machine. This single network is physically
and administratively subdivided into three
“interconnects”— the Eastern, covering the
eastern two-thirds of the United States and
Canada; the Western, encompassing most of
the rest of the two countries; and the Electric
Reliability Council of Texas (ERCOT),
covering most of Texas (Figure 1). Within
each interconnect, power flows through ac
lines, so all generators are tightly synchronized
to the
same 60-Hz
cycle. The
interconnects
are joined to
each other by
dc links, so
the coupling
is much looser
among the
interconnects
than within them. (The capacity of the
transmission lines between the interconnects
is also far less than the capacity of the
links within them.)
 |
| Figure 2. Electric
power does not travel just by the shortest route from source
to sink, but also by parallel flow paths through other parts
of the system (a). Where the network jogs around large geographical
obstacles, such as the Rocky Mountains in the West or the Great
Lakes in the East, loop flows around the obstacle are set up
that can drive as much as 1 GW of power in a circle, taking
up transmission line capacity without delivering power to consumers
(b). |
Prior to deregulation, which began in the
1990s, regional and local electric utilities
were regulated, vertical monopolies. A single
company controlled electricity generation,
transmission, and distribution in a given
geographical area. Each utility generally
maintained sufficient generation capacity to
meet its customers’ needs, and long-distance
energy shipments were usually reserved
for emergencies, such as unexpected generation
outages. In essence, the long-range connections
served as insurance against sudden
loss of power. The main exception was the
net flows of power out of the large hydropower
generators in Quebec and Ontario.
This limited use of long-distance connections
aided system reliability, because
the physical complexities of power transmission
rise rapidly as distance and the
complexity of interconnections grow.
Power in an electric network does not travel
along a set path, as coal does, for example.
When utility A agrees to send electricity
to utility B, utility A increases the amount
of power generated while utility B decreases
production or has an increased demand.
The power then flows from the “source”
(A) to the “sink” (B) along all the paths
that can connect them. This means that
changes in generation and transmission at
any point in the system will change loads
on generators and transmission lines at
every other point—often in ways not anticipated
or easily controlled (Figure 2).
To avoid system failures, the amount of
power flowing over each transmission line
must remain below the line’s capacity. Exceeding capacity
generates too much heat in a line, which can cause the line to
sag or break or can create power-supply
instability such as phase and voltage fluctuations.
Capacity limits vary, depending on
the length of the line and the transmission
voltage (Table 1). Longer lines have less
capacity than shorter ones.
In addition, for an ac power grid to
remain stable, the frequency and phase of
all power generation units must remain
synchronous within narrow limits. A generator
that drops 2 Hz below 60 Hz will
rapidly build up enough heat in its bearings
to destroy itself. So circuit breakers trip a
generator out of the system when the frequency
varies too much. But much smaller
frequency changes can indicate instability
in the grid. In the Eastern Interconnect, a
30-mHz drop in frequency reduces power
delivered by 1 GW.
If certain parts of the grid are carrying
electricity at near capacity, a small shift of
power flows can trip circuit breakers, which
sends larger flows onto neighboring lines to
start a chain-reaction failure. This happened
on Nov. 10, 1965, when an incorrectly
set circuit breaker tripped and set off
a blackout that blanketed nearly the same
area as the one in August.
After the 1965 blackout, the industry set
up regional reliability councils, coordinated
by the North American Electric Reliability
Council, to set standards to improve planning
and cooperation among the utilities. A
single-contingency-loss standard was set up
to keep the system functioning if a single
unit, such as a generator or transition line,
went out. Utilities built up spare generation
and transmission capacity to maintain a
safety margin.
In 1992, the economic rules governing
the grid began to change with passage of
the Energy Policy Act. This law empowered
the Federal Energy Regulatory Commission
(FERC) to separate electric power generation
from transmission and distribution.
Power deregulation—in reality, a change in
regulations—went slowly at first. Not until
1998 were utilities, beginning in California,
compelled to sell off their generating capacity
to independent power producers, such
as Enron and Dynergy.
 |
| Table 2. Prior
to the implementation of Federal Energy Regulatory Commission
Order 888, which greatly expanded electricity trading, the
cost of electricity, excluding fuel costs, was gradually falling.
However, after Order 888, and some retail deregulation, prices
increased by about 10%, costing consumers $20 billion a year. |
The new regulations envisioned trading
electricity like a commodity. Generating companies
would sell their power for the best
price they could get, and utilities would buy
at the lowest price possible. For this concept
to work, it was imperative to compel utilities
that owned transmission lines to carry power
from other companies’ generators in the
same way as they carried their own, even if
the power went to a third party. FERC’s
Order 888 mandated the wheeling of electric
power across utility lines in 1996. But that
order remained in litigation until March 4,
2000, when the U.S. Supreme Court validated
it and it went
into force.
In the four years
between the
issuance of Order
888 and its full
implementation,
engineers began to
warn that the new
rules ignored the
physics of the grid.
The new policies “
do not recognize
the single-machine
characteristics of
the electric-power network,” Casazza wrote
in 1998. “The new rule balkanized control
over the single machine,” he explains. “It is
like having every player in an orchestra use
their own tunes.”
In the view of Casazza and many other
experts, the key error in the new rules was to
view electricity as a commodity rather than
as an essential service. Commodities can be
shipped from point A through line B to point
C, but power shifts affect the entire singlemachine
system. As a result, increased longdistance
trading of electric power would create
dangerous levels of congestion on
transmission lines where controllers did not
expect them and could not deal with them.
The problems would be compounded,
engineers warned, as independent power
producers added new generating units at
essentially random locations determined by
low labor costs, lax local regulations, or tax
incentives. If generators were added far
from the main consuming areas, the total
quantity of power flows would rapidly
increase, overloading transmission lines. “
The system was never designed to handle long-distance wheeling,” notes Loren
Toole, a transmission-system analyst at Los
Alamos National Laboratory.
At the same time, data needed to predict
and react to system stress—such as basic
information on the quantity of energy
flows—began disappearing, treated by utilities
as competitive information and kept
secret. “Starting in 1998, the utilities
stopped reporting on blackout statistics as
well,” says Ben Carreras of Oak Ridge
National Laboratory, so system reliability
could no longer be accurately assessed.
Finally, the separation into generation
and transmission companies resulted in an
inadequate amount of reactive power, which
is current 90 deg out of phase with the voltage.
Reactive power is needed to maintain
voltage, and longer-distance transmission
increases the need for it. However, only generating
companies can produce reactive
power, and with the new rules, they do not
benefit from it. In fact, reactive-power production
reduces the amount of deliverable
power produced. So transmission companies,
under the new rules, cannot require
generating companies to produce enough
reactive power to stabilize voltages and
increase system stability.
The net result of the new rules was to
more tightly couple the system physically
and stress it closer to capacity, and at the
same time, make control more diffuse and
less coordinated—a prescription, engineers
warned, for blackouts.
In March 2000, the warnings began to
come true. Within a month of the Supreme
Court decision implementing Order 888,
electricity trading skyrocketed, as did
stresses on the grid (Figure 3). One measure
of stress is the number of transmission
loading relief procedures (TLRs)—events
that include relieving line loads by shifting
power to other lines. In May 2000, TLRs on
the Eastern Interconnect jumped to 6 times
the level of May 1999. Equally important,
the frequency stability of the grid rapidly
deteriorated, with average hourly frequency
deviations from 60 Hz leaping from
1.3 mHz in May 1999, to 4.9 mHz in May
2000, to 7.6 mHz by January 2001. As predicted,
the new trading had the effect of
overstressing and destabilizing the grid.
“Under the new system, the financial
incentive was to run things up to the limit
of capacity,” explains Carreras. In fact,
energy companies did more: they gamed
the system. Federal investigations later
showed that employees of Enron and other
energy traders “knowingly and intentionally”
filed transmission schedules designed
to block competitors’ access to the grid and
to drive up prices by creating artificial
shortages. In California, this behavior
resulted in widespread blackouts, the doubling
and tripling of retail rates, and eventual
costs to ratepayers and taxpayers of
more than $30 billion. In the more tightly
regulated Eastern Interconnect, retail prices
rose less dramatically.
After a pause following Enron’s collapse
in 2001 and a fall in electricity demand
(partly due to recession and partly to weather),
energy trading resumed its frenzy in
2002 and 2003. Although power generation
in 2003 has increased only 3% above that in
2000, generation by independent power
producers, a rough measure of wholesale
trading, has doubled. System stress, as measured
by TLRs and frequency instability, has
soared, and with it, warnings by FERC and
other groups.
 |
Figure 3. After
wholesale electricity trading began in earnest following
Federal Energy Regulatory Commission’s Order 888, stress
on the transmission grid jumped and continued to climb, as
shown by the transmission loading relief procedures (a) and
the monthly average frequency errors (b).
|
Major bank and
investment institutions
such as Morgan Stanley
and Citigroup stepped
into the place of fallen
traders such as Enron
and began buying up
power plants. But as
more players have
entered and trading
margins have narrowed,
more trades are needed
to pay off the huge
debts incurred in buying
and building generators.
Revenues also
have shrunk, because
after the California debacle,
states have refused
to substantially increase
the rates consumers pay.
As their credit ratings and stock prices fell,
utility companies began to cut personnel,
training, maintenance, and research. Nationwide,
150,000 utility jobs evaporated. “We
have a lot of utilities in deep financial trouble,”
says Richard Bush, editor of Transmission
and Distribution, a trade magazine.
The August 14 blackout, although set off
by specific chance events, became the logical
outcome of these trends (Figure 4). Controllers
in Ohio, where the blackout started,
were overextended, lacked vital data, and
failed to act appropriately on outages that
occurred more than an hour before the
blackout. When energy shifted from one
transmission line to another, overheating
caused lines to sag into a tree. The snowballing
cascade of shunted power that rippled
across the Northeast in seconds would
not have happened had the grid not been
operating so near to its transmission capacity.
How to fix it
The conditions that caused the August
14th blackout remain in place. In fact, the
number of TLRs and the extent of frequency
instability remained high after August 14
until September’s cool weather reduced
stress on the grid. What can be done to
prevent a repetition next summer?
One widely supported answer is to change
the grid physically to accommodate the new
trading patterns, mainly by expanding transmission
capacity. The DOE and FERC, as
well as organizations supported by the utilities,
such as the Electric Power Research
Institute and the Edison Electric Institute,
advocate this approach. In reports before
and after the blackout, they urged expanding
transmission lines and easing environmental
rules that limit their construction.
The logic is simple: if increased energy trading
causes congestion and, thus, unreliability,
expand capacity so controllers can switch
energy from line to line without overloading.
 |
Figure 4. Blackout
sequence of events, August 14, 2003
1:58 p.m. The Eastlake, Ohio,
generating plant shuts down. The plant is owned by First
Energy, a company that had experienced extensive recent
maintenance problems, including a major nuclear-plant
incident.
3:06 p.m. A First Energy 345-kV transmission
line fails south of Cleveland, Ohio.
3:17 p.m. Voltage dips temporarily
on the Ohio portion of the grid. Controllers take no action,
but power shifted by the first failure onto another power
line causes it to sag into a tree at 3:32 p.m., bringing
it offline as well. While Mid West ISO and First Energy
controllers try to understand the failures, they fail to
inform system controllers in nearby states.
3:41 and 3:46 p.m. Two breakers connecting
First Energy’s grid with American Electric Power
are tripped.
4:05 p.m. A sustained power surge on
some Ohio lines signals more trouble building.
4:09:02 p.m. Voltage sags deeply as
Ohio draws 2 GW of power from Michigan.
4:10:34 p.m. Many transmission lines
trip out, first in Michigan and then in Ohio, blocking
the eastward flow of power. Generators go down, creating
a huge power deficit. In seconds, power surges out of the
East, tripping East coast generators to protect them, and
the blackout is on.
(Orbital Imaging Corp; processing by
NASA Goddard Space Flight Center)
|
To pay the extensive costs, the utilities
and the DOE advocate increases in utility
rates. “The people who benefit from the
system have to be part of the solution
here,” Energy Secretary Spencer Abrams
said during a television interview. “That
means the ratepayers are going to have to
contribute.” The costs involved would certainly
be in the tens of billions of dollars.
Thus, deregulation would result in large
cost increases to consumers, not the savings
once promised (Table 2).
But experts outside the utility industry
point to serious drawbacks in the build-more
solution other than increasing the
cost of power. For one, it is almost impossible
to say what level of capacity will accommodate
the long-distance wholesale trading.
The data needed to judge that is now
proprietary and unavailable in detail. Even
if made available to planners, this data
refers only to the present. Transmission
lines take years to build, but energy flows
can expand rapidly to fill new capacity, as
demonstrated by the jump in trading in the
spring of 2000. New lines could be filled
by new trades as fast as they go up.
The solution advocated by deregulation
critics would revise the rules to put them
back into accord with the grid physics. “
The system is not outdated, it is just misused,”
says Casazza. “We should look hard
at the new rules, see what is good for the
system as a whole, and throw out the rest.”
Some changes could be made before next
summer, and at no cost to ratepayers. For
one thing, FERC or Congress could rescind
Order 888 and reduce the long-distance
energy flows that stress the system. Second,
the data on energy flows and blackouts
could again be made public so that
planners would know what power flows are
occurring and the reliability records of the
utilities. Other changes, such as rehiring
thousands of workers to upgrade maintenance,
would take longer and might require
rewriting regulations and undoing more of
the 1992 Energy Act.
These changes also would have costs,
but they would be borne by the shareholders
and creditors of the banks and energy
companies who bet so heavily on energy
trading. With cash flows dwindling and
debt levels high, many of these companies
or their subsidiaries might face bankruptcy
if energy trading is curtailed. The decision
will ultimately fall to Congress, where hearings
are scheduled for the fall. However the
decision turns out, what is nearly certain is
that until fixed, the disconnect between the
grid’s economics and physics will cause
more blackouts in the future.
Further reading
Casazza, J. A. Blackouts: Is the Risk
Increasing? Electrical World 1998, 212 (4),
62–64.
Casazza, J. A.; Delea, F. Understanding
Electric Power Systems: An Overview of the
Technology and the Marketplace; Wiley: New
York, 2003; 300 pp.
Hale, D. R. Transmission Data and Analysis:
How Loose is the Connection?; available
here.
Loose, V. W.; Dowell, L. J. Economic and
Engineering Constraints on the Restructuring
of the Electric Power Industry;
available
here.
Mountford, J. D.; Austria, R. R. Power
Technologies Inc. Keeping the lights on!
IEEE Spectrum 1999, 36 (6), 34–39.
National Transmission
Grid Study Report; available
here.
Tucker, R. J. Facilitating Infrastructure
Development: A Critical Role for Electric
Restructuring. Presented at the National
Energy Modeling System/Annual Energy
Outlook Conference, Washington, DC,
March 10, 2003; available
here.
|